Construction Schedule Week of 01/12:  

Crew #1: Lateral CIPP Lining – Argyle Ave and Bishop Road (Day)
Crew #2: Lateral CIPP Lining – Walden Street (Day)
Crew #3: Lateral CIPP Lining – Kenney Ave, Hawthorne Road and Outlook Ave (Day)
Crew #4: Lateral CCTV and Cleaning – Trout Brook (Craigmoor/Duffield), Kingswood Road, Pleasant Street and Hilltop Drive (Day)
Crew #5: Manhole Work – Hilltop Drive 
Crew #6: Emergency Point Repairs – Standby (Day)

PROJECT INFORMATION MATERIALS
Stakeholder Outreach Meeting Presentation 2.27.25
Project Area Map
Project Area Map (Broken Down By Zone)
Project Description / List of Streets
Project Presentation to West Hartford Community Planning and Economic Development Committee