NEWS RELEASE
May 7, 2003
MDC to
Install Sewer in West HartfordWEST
HARTFORD – A contractor for the Metropolitan District Commission (MDC) will
install a new sanitary sewer to serve residents of Long View Road in West
Hartford.
The
contractor, VMS Construction Co. of Vernon, is scheduled to begin the $181,205
project on May 12. Completion is expected by the end of June.
The
new sewer will be approximately 1,020 feet long and serve 16 properties, which
currently do not have sanitary sewers.
Work
will be performed from 7:30 a.m. to 4 p.m. weekdays. During construction,
traffic may be reduced to one lane.
# # #
| Editors: for further information contact | Matt Nozzolio (860) 278-7850, ext. 3209 |